Related provisions for BIPRU 7.10.122
1 - 1 of 1 items.
The VaR model review process may be conducted through a series of visits covering various aspects of a firm's control and IT environment. Before these visits the appropriate regulator may ask the firm to provide some information relating to the firm'sVaR model permission request accompanied by some specified background material. The VaR model review visits are organised on a timetable that allows the firm being visited sufficient time to arrange the visit and provide the appropriate
Where backtesting reveals severe problems with the basic integrity of the VaR model, the appropriate regulator may withdraw model recognition. In particular, if ten or more backtesting exceptions are recorded in a 250 business day period, the appropriate regulator may apply a plus factor greater than one or the appropriate regulator may consider revoking a firm'sVaR model permission. The appropriate regulator may also consider revoking a firm'sVaR model permission if ten or more
The minimum multiplication factor, for VaR and stressed VaR,3 will never be less than three. If the appropriate regulator does set the minimum multiplication factor, for VaR and stressed VaR,3 above three the VaR model permission will have a table that sets out the reasons for that add on and specify how much of the add on is attributable to each reason (see BIPRU 7.10.121R). If there are weaknesses in the VaR model that may otherwise be considered a breach of the minimum standards
If a firm ceases to meet any of the requirements set out in BIPRU 7.10, the appropriate regulator's policy is that the VaR model permission should cease to have effect. In part this will be achieved by making it a condition of a firm'sVaR model permission that it complies at all times with the minimum standards referred to in BIPRU 7.10.26R - BIPRU 7.10.53R. Even if they are not formally included as conditions, the appropriate regulator is likely to consider revoking the VaR model