Related provisions for DTR 1C.2.5
1This table belongs to COLL 7.4.1 G (4) (Explanation of COLL 7.4)
Summary of the main steps in winding up an AUT or terminating a sub-fund under FCArules Notes: N = Notice to be given to the FCA under section 251 of the Act. E = commencement of winding up or termination W/U = winding up FAP = final accounting period (COLL 7.4.5 R (4)) |
|||
Step number |
Explanation |
When |
|
1 |
Receive FCA approval |
N + one month On receipt of notice from the FCA |
Section 251 of the Act |
2 |
Normal business ceases; notify unitholders |
E |
7.4.3R |
3 |
Trustee to realise and distribute proceeds |
ASAP after E |
7.4.4R(1) to (5) |
4 |
Within 4 months of FAP |
7.4.5R(5) |
|
5 |
Request FCA to revoke relevant authorisation order |
On completion of W/U |
7.4.4R(6) |
Sections 87H and 87I of the Act provide:
Prospectus approved in another EEA State |
||||
87H |
(1) |
A prospectus approved by the competent authority of an EEA State other than the United Kingdom is not an approved prospectus for the purposes of section 85 unless that authority has notified ESMA and provided the competent authority with -3 |
||
(a) |
a certificate of approval; |
|||
(b) |
a copy of the prospectus as approved; and |
|||
(c) |
if requested by the [FCA], a translation of the summary of the prospectus. |
|||
(2) |
A document is not a certificate of approval unless it states that the prospectus - |
|||
(a) |
has been drawn up in accordance with the prospectus directive; and |
|||
(b) |
has been approved, in accordance with that directive, by the competent authority providing the certificate. |
|||
(3) |
A document is not a certificate of approval unless it states whether (and, if so, why) the competent authority providing it authorised, in accordance with the prospectus directive, the omission from the prospectus of information which would otherwise have been required to be included. |
|||
3(3A) |
The competent authority must publish on its website a list of certificates of approval provided to it in accordance with this section. |
|||
3(3B) |
The list referred to in subsection (3A) must - |
|||
(a) |
be kept up-to-date; |
|||
(b) |
retain items on it for a period of at least 12 months; and |
|||
(c) |
include hyperlinks to any certificate of approval and prospectus published on the website of - |
|||
(i) |
the competent authority of the EEA State which provided the certificate; |
|||
(ii) |
the issuer; or |
|||
(iii) |
the regulated market where admission to trading is sought. |
|||
(4) |
"Prospectus" includes a supplementary prospectus. |
Provision of information to host Member State |
|||
87I |
(1) |
The [FCA] must, if requested to do so, supply the competent authority of a specified EEA State with – |
|
(a) |
a certificate of approval; |
||
(b) |
a copy of the specified prospectus (as approved by the [FCA]); and |
||
(c) |
a translation of the summary of the specified prospectus (if the request states that one has been requested by the other competent authority).2 |
||
(1A)2 |
If the competent authority supplies a certificate of approval to the competent authority of the specified EEA State, it must also supply a copy of that certificate to - |
||
(a) |
the person who made the request under this section; and |
||
(b) |
ESMA. |
||
(2) |
Only the following may make a request under this section – |
||
(a) |
the issuer of the transferable securities to which the specified prospectus relates; |
||
(b) |
a person who wishes to offer the transferable securities to which the specified prospectus relates to the public in an EEA State other than (or as well as) the United Kingdom; |
||
(c) |
a person requesting the admission of the transferable securities to which the specified prospectus relates to a regulated market situated or operating in an EEA State other than (or as well as) the United Kingdom. |
||
(3) |
A certificate of approval must state that the prospectus – |
||
(a) |
has been drawn up in accordance with this Part and the prospectus directive; and |
||
(b) |
has been approved, in accordance with those provisions, by the [FCA]. |
||
(4) |
A certificate of approval must state whether (and, if so, why) the [FCA] authorised, in accordance with section 87B, the omission from the prospectus of information which would otherwise have been required to be included. |
||
(5) |
The [FCA] must comply with a request under this section – |
||
(a) |
if the prospectus has been approved before the request is made, within 3 working days beginning with the date the request is received2; or 2 |
||
(b) |
if the request is submitted with an application for the approval of the prospectus, on the first working day after the date on which it approves the prospectus. |
||
(6) |
“Prospectus” includes a supplementary prospectus. |
||
(7) |
“Specified” means specified in a request made for the purposes of this section. |
Table: FCA-approved persons forms
Form |
Purpose |
Handbook requirement |
|
the relevant Form A |
The relevant online form on the FCA and PRA'sonline notification and application system3 or the form in SUP 10A Annex 4D (See Note) 11 |
Application to perform controlled functions under the approved persons regime |
|
Form B |
Notice to withdraw an application to perform controlled functions under the approved persons regime |
||
Form C |
Notice of ceasing to perform controlled functions |
||
Form D |
Notification of changes in personal information or application details |
||
Form E |
The relevant online form on the FCA and PRA'sonline notification and application system3 system or the form in SUP 10A Annex 8D (See Note) 11 |
Internal transfer of an approved person |
|
Note: The form in the SUP annex shown is to be used by credit unions, and by other firms only in the event of a failure of the information technology systems used by the FCA. See the relevant "Handbook requirement" |