Article 30 Content of the application to be submitted by the institution for the purposes of Article 77 of Regulation (EU) No 575/2013

  1. (1)

    The application referred to in Article 29 shall be accompanied by the following information:

    1. (a)

      a well-founded explanation of the rationale for performing one of the actions referred to in paragraph 1 of Article 29;

    2. (b)

      information on capital requirements and capital buffers, covering at least a three year period, including the level and composition of own funds before and after the performing of the action and the impact of the action on regulatory requirements;

    3. (c)

      the impact on the profitability of the institution of a replacement of a capital instrument as specified in point (a) of Article 78(1) of Regulation (EU) No 575/2013;

    4. (d)

      an evaluation of the risks to which the institution is or might be exposed and whether the level of own funds ensures an appropriate coverage of such risks, including stress tests on main risks evidencing potential losses under different scenarios;

    5. (e)

      any other information considered necessary by the competent authority for evaluating the appropriateness of granting a permission according to Article 78 of Regulation (EU) No 575/2013.

  2. (2)

    The competent authority shall waive the submission of some of the information listed in paragraph 2 where it is satisfied that this information is already available to it.