Content Options:

Content Options

Subsection 2 Process in the absence of joint decision on group resolution plan and resolvability assessment

Article 73 Partial disagreement

  1. (1)

    Where one or more of the resolution authorities of subsidiaries disagree with the group resolution plan and resolvability assessment, the group-level resolution authority and the resolution authorities of subsidiaries which do not disagree pursuant to Article 13(7) of the Directive 2014/59/EU shall follow all relevant steps set out in Articles 70, 71 and 72 for drafting, reaching and communicating the joint decision on the group resolution plan and resolvability assessment.

  2. (2)

    The joint decision taken on the group resolution plan and resolvability assessment shall be set out in a document that contains all of the items set out in Article 70.

  3. (3)

    A summary of views expressed by the resolution authorities of subsidiaries who were involved in the initial joint decision process on the group resolution plan and resolvability assessment but disagreed to it shall be included. In particular, the summary shall include references to all issues that led to disagreement.

Article 74 Elements of communication of individual decisions

  1. (1)

    In the absence of a joint decision between the resolution authorities within four months in accordance with Article 13(5) of Directive 2014/59/EU, the decision taken by the group-level resolution authority on the group resolution plan and resolvability assessment shall be communicated in writing to the resolution college members by means of a document containing all of the following items:

    1. (a)

      the name of the group-level resolution authority;

    2. (b)

      the name of the Union parent undertaking;

    3. (c)

      references to the applicable Union and national law relating to the preparation, finalisation and application of the decision;

    4. (d)

      the date of the decision;

    5. (e)

      the group resolution plan and resolvability assessment including any measures to address or remove substantive impediments to resolvability in accordance to Article 17(4), (5) and (6) of Directive 2014/59/EU, subject to which the decision is taken. Where the Union parent undertaking is in the process of implementing those measures, the timeline for their implementation shall be also provided;

    6. (f)

      the names of the resolution college members and observers involved, in accordance with the terms and conditions of observers' participation, in the joint decision process on the group resolution plan and resolvability assessment, along with a summary of the views expressed by those authorities and information on issues leading to disagreement;

    7. (g)

      comments of the group-level resolution authority on the views expressed by resolution college members and observers, in particular on issues leading to disagreement.

  2. (2)

    In the absence of a joint decision between the resolution authorities within four months in accordance with Article 13(6) of Directive 2014/59/EU, the resolution authorities drawing up individual resolution plans shall transmit to the group-level resolution authority a document that contains all of the following items:

    1. (a)

      the name of the resolution authority taking the decision;

    2. (b)

      the name of the entity or entities under the jurisdiction of the resolution authority to which the decision relates and applies;

    3. (c)

      references to the applicable Union and national law relating to the preparation, finalisation and application of the decision;

    4. (d)

      the date of the decision;

    5. (e)

      the resolution plan and the assessment of resolvability of the entities under their jurisdiction including any measures to address or remove substantive impediments to resolvability in accordance to Article 17(4), (5) and (6) of Directive 2014/59/EU, subject to which the decision is taken. Where the entities are in the process of implementing these measures, then the timeline for their implementation shall be also provided;

    6. (f)

      the name of the group-level resolution authority along with explanations on the reasons for disagreement with the proposed group resolution plan and resolvability assessment.

  3. (3)

    Where the EBA has been consulted, the decisions taken in the absence of a joint decision in accordance with Article 13(5) and (6) of Directive 2014/59/EU shall include an explanation as to why the advice of the EBA was not followed.

Article 75 Communication of individual decisions in the absence of a joint decision

  1. (1)

    In the absence of a joint decision between the group-level resolution authority and the resolution authorities of subsidiaries within the time period referred to in Article 13(4) of Directive 2014/59/EU, all decisions referred to in Article 13(5) and (6) of that Directive shall be communicated in writing by the relevant resolution authorities of subsidiaries to the group-level resolution authority, by the latest of the following dates:

    1. (a)

      the date one month after the expiry of the time period referred to in Article 13(4) of Directive 2014/59/EU;

    2. (b)

      the date one month after the provision of any advice by the EBA following a request for consultation in accordance with the third subparagraph of Article 13(4) of Directive 2014/59/EU;

    3. (c)

      the date one month after any decision taken by the EBA in accordance with the second subparagraph of Article 13(5) or Article 13(6) of Directive 2014/59/EU or any other date set by the EBA in such a decision.

  2. (2)

    The group-level resolution authority shall notify without undue delay its own decision and the decisions referred to in paragraph 1 to the other resolution college members.