RCB 3.3 Asset pool notifications

Form of notifications1

RCB 3.3.1DRP

The issuer must send to the FCA, information relating to the asset pool, in the form set out in RCB 3 Annex 2D (asset notification form), and information relating to the regulated covered bonds issued under the programme, in the form set out in RCB 3 Annex 3 D (asset and liability profile form).1

RCB 3.3.2DRP

The issuer must send the asset notification form1 to the FCA each month following the registration date, and the asset and liability profile form to the FCA1 within one month of the end of each quarter following the registration date.

1
RCB 3.3.2ADRP

1The issuer must send to the FCA loan-by-loan level data relating to the asset pool in the form set out in RCB 3 Annex 7A D within one month of the end of each quarter following any issuance of regulated covered bonds after 1 January 2013. Guidance on how to complete this form is set out in RCB 3 Annex 7B G.

Notifications by the owner

RCB 3.3.3DRP

If the issuer is in insolvency, the owner must send to the FCA the notifications set out at RCB 3.3.1 D and RCB 3.3.2A D1 by the same dates as the dates the notifications under those directions are due.

1

Due diligence

RCB 3.3.4GRP

The issuer or the owner, as the case may be, should carry out, or make arrangements to carry out, appropriate due diligence to check that the analysis in the information provided to the FCA is correct.

1

Addition or removal of assets from the asset pool1

RCB 3.3.5DRP

1If the issuer or the owner (as the case may be) proposes to add or remove assets to or from the asset pool which change the level of over collateralisation by 5% or more, it must notify the FCA using the form set out in RCB 3 Annex 2 D (asset notification form) at least 5 business days prior to the proposed transfer, giving expected details of the size and composition of the transfer.