CTPS 8.2 Intermediate incident report

CTPS 8.2.1R

1A critical third party must, as soon as is practicable after any significant change in circumstances from that described in the initial report submitted under CTPS 8.1.1R (Initial incident report) and any intermediate incident report already submitted under this rule (including the CTP operational incident being resolved) and in so far as it is aware at the relevant time, provide the regulators and the affected firms with information further to that already disclosed in relation to the CTP operational incident, including but not limited to:

  1. (1)

    any information that the critical third party reasonably considers will assist the regulators and affected firms in understanding the nature and extent of the CTP operational incident;

  2. (2)

    any steps taken to resolve the CTP operational incident;

  3. (3)

    if the CTP operational incident has been resolved, the time and date it was resolved; and

  4. (4)
    1. (a)

      any other information the critical third party reasonably considers to be relevant to affected firms; and

    2. (b)

      to the regulators only, any other information the critical third party reasonably considers to be relevant to the regulators.